Consultation So Far

We started engaging with the local community about the plans for Phase 3 in 2018. Thank you to everyone who’s been involved so far, including the Residents’ Steering Group, the Design Working Group and all who have shared their thoughts.

Our engagement

2018

September

Initial consultation at Portobello’s Park Party

2018

November – May 2019

Design workshops with Residents’ Design Working Group

2019

June

Public consultation events

2019

July

Pop-up at Golborne Festival

2019

July – September

Further design workshop with Residents’ Design Working Group

2019

October – November

Door-knocking on Wornington Green estate and neighbouring streets

2020

January

Golborne Road pop-up

2020

November – WE ARE HERE

Second public consultation and online feedback sessions

2021

Spring – Submission

2021

Autumn – Determination

2024

Construction start

2028

Target completion

Design Working Group

Since November 2018, we have held a series of meetings with the Residents’ Design Working Group to discuss the proposals for Phase 3 and discuss their ideas and insights on key aspects of the design.

The Catalyst team would like to thank the group for their commitment and valuable input.

What’s next?

Following this final round of public consultation, we will work to finalise our detailed designs, taking into account the feedback received from the community as much as possible.

We’re aiming to submit a planning application to the Council in Spring 2021.

People at consultation event
People at consultation event
People at consultation event
People at consultation event